What Is "Float" in Project Management And Types, Benefits, Tools, Examples, And How to Calculate?
Written By : Bakkah
27 Jul 2024
float in project management is the slack time within a schedule, allowing activity delays without affecting project duration or subsequent tasks. It's vital for identifying critical activities, prioritizing tasks, and managing resources efficiently. Understanding float helps optimize schedules, allocate resources effectively, and mitigate risks of project delays.
In project management, there are two types of float: Total Float and Free Float. Total Float is the maximum delay an activity can have without delaying the project's completion. Free Float is the maximum delay without delaying its successor's start. Understanding and managing float is essential for meeting project timelines and optimizing resources.
What is Float Time in Project Management
In project management, "float" refers to the amount of time that a task or activity can be delayed without causing a delay to the project's overall completion date. Also known as slack or total float, float represents the flexibility in the project schedule and indicates the cushion available for scheduling individual activities.
Understanding float is crucial for project managers to effectively manage project schedules, allocate resources, and identify critical paths within a project. By analyzing float, project managers can prioritize activities, optimize scheduling, and mitigate risks associated with potential delays.
What is Float in PERT and CPM?
In both PERT (Program Evaluation and Review Technique) and CPM (Critical Path Method), float refers to the amount of time that an activity can be delayed without delaying the project's overall completion date. Float is also known as slack or buffer.
In PERT, float is typically referred to as total float or slack. Total float represents the time that an activity can be delayed without delaying the project's completion date. It is calculated as the difference between the latest allowable finish time and the earliest allowable finish time for an activity.
In CPM, float is often divided into two types: total float and free float. Total float, similar to PERT, represents the time an activity can be delayed without delaying the project's completion. On the other hand, free float represents the amount of time an activity can be delayed without delaying the early start of any succeeding activities. It is a more restrictive form of float as it considers only the immediate successor activities.
Overall, float in both PERT and CPM is crucial for project managers to identify critical activities, manage project schedules, and ensure timely project completion.
What is The Float on The Critical Path?
The float on the critical path, also known as the critical path float or critical path slack, is always zero. This is because the critical path represents the longest sequence of dependent tasks in a project, and any delay in activities along the critical path will directly impact the project's overall duration.
Therefore, there is no flexibility or float available on the critical path, as any delay in critical path activities will result in a delay in the project's completion.
Independent Float in Project Management
Independent float, also known as Interfering Float or Path Float, is a type of float in project management that refers to the amount of time an activity can be delayed without delaying the early start of any successor activity.
In other words, it represents the flexibility of an activity within its path without affecting other parallel paths or activities in the project network. Here's how to calculate Independent Float:
- Calculate Early Start (ES) and Early Finish (EF) for each activity in the project network.
- Identify the immediate successor activities for each activity.
- Calculate the Free Float (FF) for each activity using the formula: FF = ES of immediate successor - EF of current activity - Duration of current activity + 1.
- Subtract the Free Float (FF) from the Total Float (TF) to obtain the Independent Float (IF) for each activity.
Independent Float helps project managers identify critical activities within a path that have limited flexibility and may require closer monitoring to ensure the timely completion of the project. It allows project teams to focus on activities that have the least amount of flexibility and may impact the overall project schedule if delayed.
Benefits of Float in Project Management
Float in project management plays a crucial role in enhancing schedule flexibility, managing risks, optimizing resources, improving time management, and facilitating contingency planning to ensure the successful completion of projects within the defined timeline. Float in project management provides several benefits, including:
1. Schedule Flexibility
Float allows project managers to have some degree of flexibility in managing project schedules. It provides a buffer of time for non-critical activities, which can be adjusted without affecting the overall project completion date.
2. Risk Management
Float helps in identifying and managing risks associated with project schedules. By analyzing float values, project managers can prioritize critical tasks and allocate resources more effectively to ensure timely completion of essential activities.
3. Resource Optimization
Float allows project managers to optimize resource allocation by identifying non-critical activities that can be rescheduled or adjusted to accommodate resource constraints without impacting the project's critical path.
4. Time Management
Float provides a clear understanding of the project's schedule and allows project managers to allocate time effectively. It helps in identifying tasks that can be completed earlier or later without affecting the project's overall timeline.
5. Contingency Planning
Float provides a contingency buffer for unforeseen delays or changes in project activities. Project managers can use the float to develop contingency plans and mitigate the impact of unexpected events on project schedules.
Float in Project Management Tools
Float in project management tools refers to the feature enabling calculation, visualization, and management of slack time in project schedules. These tools aid managers in efficiently handling project timelines and resources by discerning critical activities and optimizing schedules. Key features include:
1. Float Calculation
Project management tools automatically calculate float or slack time for each activity based on its duration, dependencies, and constraints. This calculation considers the difference between the early start, early finish, late start, and late finish times for each activity.
2. Float Visualization
These tools provide visual representations of project schedules, including Gantt charts or network diagrams, highlighting critical paths and displaying float or slack time for non-critical activities. This visualization helps project managers identify where float exists and how much flexibility they have in scheduling non-critical tasks.
3. Critical Path Analysis
Project management tools analyze project schedules to identify the critical path and determine the total float available in the schedule. They highlight critical activities that have zero float and non-critical activities with positive float, allowing project managers to focus on managing critical tasks and optimizing non-critical ones.
4. Resource Management
Some project management tools integrate float management with resource allocation and resource leveling features. They help project managers balance resource utilization across critical and non-critical activities by considering float and resource availability.
5. Scenario Planning
Float management tools enable scenario planning and "what-if" analysis by allowing users to adjust activity durations, dependencies, or resource assignments to explore different scheduling scenarios. Project managers can evaluate the impact of these changes on project timelines and resource utilization.
6. Alerts and Notifications
Advanced project management tools may include alerting and notification features to notify project managers of changes in float values or potential schedule conflicts. This helps project managers proactively address schedule issues and take corrective actions to prevent delays.
Types of Float in Project Management
In project management, two types of float are vital: total float and free float. Understanding them enables effective schedule management, resource allocation, and risk mitigation. Float analysis aids in identifying critical paths, prioritizing activities, and optimizing schedules for timely project completion.
1. Total Float (Total Slack)
Total float in project management, also known as total slack, represents the time an activity can be delayed without delaying the project's overall completion date. It indicates the flexibility in the project schedule and considers all dependencies and constraints within the project network. Total float is calculated by subtracting the early start date of an activity from its late start date or the early finish date from its late finish date.
2. Free Float
free float in project management is the amount of time an activity can be delayed without affecting the early start of any successor activity. Unlike total float, which considers the overall project completion date, free float focuses on the immediate successor activities. It represents the maximum amount of delay that can occur in an activity without impacting subsequent activities. Free float is calculated by subtracting the early finish date of an activity from the early start date of its successor activity minus one.
Float in Project Management Example
Let's consider a simple construction project with three main activities: Excavation, Foundation Pouring, and Building Construction.
- Excavation (Activity A): Estimated 5 days
- Foundation Pouring (Activity B): Estimated 7 days
- Building Construction (Activity C): Estimated 10 days
Activity B (Foundation Pouring) can only start after Activity A (Excavation) is completed. Similarly, Activity C (Building Construction) can only start after Activity B (Foundation Pouring) is completed.
Now, let's assume the project manager has identified the critical path, which is the longest path through the project network, as follows:
Excavation (5 days) → Foundation Pouring (7 days) → Building Construction (10 days)
How to Calculate Total Float?
For Activity A (Excavation), total float examples are calculated as follows:
Total Float = Late Start - Early Start
Assuming the project deadline is 30 days, Activity A can start on Day 1 and must finish by Day 5 to avoid delaying the project's completion. Therefore, the total float for Activity A would be:
Total Float = 30 - 5 = 25 days
Free Float
For Activity A (Excavation), the free float formula is calculated as follows:
Free Float = Early Start of Successor - Early Finish
Assuming Activity B (Foundation Pouring) can start on Day 6 (immediately after the completion of Activity A) and must start no later than Day 7 to avoid delaying Activity B. Therefore, the free float for Activity A would be:
- Free Float = 6 - 5 - 1 = 0 days
In this example, Activity A (Excavation) has a total float of 25 days, indicating that it can be delayed by up to 25 days without affecting the project's overall completion date. However, it has a free float of 0 days, meaning any delay in Activity A would impact the immediate successor activity (Activity B) and potentially delay the project's critical path.
Total Float VS Free Float
Total float and free float are two important concepts in project management that relate to scheduling and the flexibility of activities within a project network. Total float measures the overall flexibility of an activity within the project schedule, while free float specifically assesses the flexibility of an activity to its immediate successor activity. Here's the difference between them:
Difference |
Total Float |
Free Float |
Definition |
Total float, also known as total slack, refers to the time an activity can be delayed without delaying the project's overall completion date. |
Free float is a subset of total float and refers to the amount of time an activity can be delayed without delaying the early start date of any immediate successor activity. |
Calculation |
It is calculated as the difference between the Late Start and Early Start of an activity. |
It is calculated as the difference between the Early Start of the successor activity and the Early Finish of the current activity minus one. |
Impact on Project Schedule |
Total Float affects the project's overall completion date and determines the flexibility in scheduling non-critical activities. |
Free Float affects the scheduling of immediate successor activities and determines the flexibility in scheduling critical activities without delaying subsequent activities. |
Use in Schedule Management |
It helps project managers identify activities that have flexibility in their start and finish dates without impacting the project's deadline. |
It helps project managers identify activities that can be delayed without affecting the start of their immediate successor activities. |
Representation |
It is represented in terms of days or units of time that an activity can be delayed. |
It is also represented in terms of days or units of time that an activity can be delayed, but specifically to the start of its immediate successor activity. |
How to Calculate Float in Project Management?
Float in project management can be calculated using the Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF) dates of activities in the project network. Here's how to calculate float:
1. Calculate Early Start (ES) and Early Finish (EF)
Early Start (ES) is the earliest point in time when an activity can start. It is determined by the earliest finish time of its predecessor activities.
Early Finish (EF) is the earliest point in time when an activity can be completed. It is calculated by adding the activity's duration to its Early Start time.
2. Calculate Late Start (LS) and Late Finish (LF)
Late Finish (LF) is the latest point in time when an activity must be completed to avoid delaying the project's overall finish time. It is determined by subtracting the activity's total float from its Early Finish time.
Late Start (LS) is the latest point in time when an activity can start without delaying the project's overall finish time. It is calculated by subtracting the activity's duration from its Late Finish time.
3. Calculate Float
Total Float (TF) is calculated as the difference between the Late Start (LS) and Early Start (ES) times, or Late Finish (LF) and Early Finish (EF) times, for each activity. It represents the time an activity can be delayed without delaying the project's completion.
Free Float (FF) is calculated as the difference between the Early Start (ES) of the immediate successor activity and the Early Finish (EF) of the current activity, minus one day (to account for continuity). It represents the amount of time an activity can be delayed without delaying the start of the next activity.
By calculating the Early Start, Early Finish, Late Start, and Late Finish times for each activity and applying the formulas for Total Float and Free Float, project managers can determine the flexibility of activities within the project schedule.
Elevate Your Skills in Governance and Service Management with Bakkah's Expert Courses!
Unlock the door to success in the dynamic world of IT service management with Bakkah's top-notch Governance and Service Management courses. Whether you're a seasoned professional or just starting your journey in IT, our courses are designed to equip you with the knowledge and skills needed to excel in today's competitive industry.
Explore cutting-edge methodologies and best practices with our ITIL® 4 Foundation and COBIT® 5 Foundation courses, and gain a solid foundation in IT service management frameworks that are globally recognized and respected.
Dive deep into the world of DevOps with our DevOps Fundamentals and DevOps Leadership courses, and learn how to streamline IT processes, improve collaboration between development and operations teams, and accelerate the delivery of high-quality software solutions.
Take your ITIL® expertise to the next level with our ITIL® 4 Specialist: Create, Deliver and Support (CDS), and master the essential skills needed to design, deliver, and support IT services that drive business success.
Don't miss this opportunity to enhance your skills and advance your career in IT Governance and Service Management with Bakkah's industry-leading courses. Enroll now and take the first step toward achieving your professional goals!
Conclusion
Overall, float in project management is a critical concept that refers to the flexibility or slack time available within a project schedule. It encompasses both total float and free float, which are essential for project managers to understand to effectively manage project schedules and mitigate potential risks. Total float represents the amount of time a task can be delayed without delaying the project's overall completion date, while free float indicates the amount of time a task can be delayed without affecting the start of any subsequent tasks.
Understanding and managing float in project schedules allows project managers to optimize resource utilization, minimize schedule conflicts, and ensure timely project delivery. By identifying critical tasks and leveraging float strategically, project managers can proactively address schedule constraints and make informed decisions to keep projects on track. Ultimately, float empowers project managers to navigate the complexities of project scheduling with confidence, delivering successful outcomes and meeting stakeholder expectations.